πŸ‡±πŸ‡· Monrovia, Liberia Β· Bank Branch

50kW Solar System for Bank Branch in Liberia: 150kWh Storage

50kWSolar PV
150kWhBattery Storage
$2,300/moSaved / Month
13 monthsPayback

Project Background

This bank branch in Monrovia depended on diesel generators for 60% of its operating hours. Liberia's grid delivers power only intermittently, and a bank cannot tolerate downtime β€” ATMs, security systems, and transaction servers must run 24/7. Monthly diesel and grid costs totaled $2,800.

The Challenge: 24/7 Uptime on an Unstable Grid

The branch required zero-interruption power for banking operations. Diesel generators were noisy, required constant maintenance, and fuel price volatility made budgeting impossible. The bank needed a silent, reliable, and cost-predictable alternative.

The Solution: 50kW Solar + 150kWh LFP Storage

Mars Solar designed a hybrid solar power system with battery storage sized to carry the full branch load through nights and grid outages. The LFP battery bank provides 8+ hours of autonomy at average load, with seamless switchover in milliseconds.

Solar PV Capacity50 kW (Tier-1 mono PERC modules)
Battery Energy Storage150 kWh LFP, 6,000-cycle rated
InvertersHybrid inverter, 3-phase 50kW
System TypeHybrid: grid + solar + battery
Autonomy8+ hours at average load
Installation4 days, Mars Solar certified team

Results & ROI

The solar power system now covers 85% of the branch's annual energy needs. Monthly energy costs fell from $2,800 to under $500. The generators now run only during scheduled maintenance tests. Noise complaints from neighboring offices stopped entirely.

Monthly savings$2,300
Annual savings$27,600
Payback period13 months
Energy cost reduction82%
Grid independence85% of annual demand

β€œOur branch has not experienced a single minute of downtime since installation. The ROI was confirmed within 13 months by our own accounting.”

β€” Branch Manager, Monrovia Bank

Implementation Timeline

Day 1–3
Load audit, site survey, and system design
Week 2–5
Manufacturing and factory testing
Week 6–9
Shipping to Monrovia
Week 10
Installation, commissioning, staff training

Project Gallery

Bank Branch solar power system β€” Liberia 1
Bank Branch solar power system β€” Liberia 2
Bank Branch solar power system β€” Liberia 3

Why This Configuration

A bank branch is a small load with an unforgiving availability requirement. ATMs, teller terminals, the branch server and the VSAT or fibre link all have to stay up β€” and a grid-tied system without storage shuts down exactly when the grid drops, which is the one moment the branch cannot afford it. That is why this system is hybrid rather than grid-tied-only.

Autonomy, not capacity, set the battery size. 150 kWh delivering eight-plus hours at the branch's average load implies an average critical draw near 19 kW (150 kWh Γ· 8 h) β€” teller positions, ATM, lighting, server and communications, but deliberately not air conditioning. Including the chiller plant would have roughly doubled the pack for no compliance benefit.

Design Notes for Similar Sites

  • Separate critical load from comfort load before sizing storage. Branch uptime does not require air conditioning.
  • Specify cycle life, not just capacity: 6,000 cycles at the depth of discharge you will actually use.
  • Confirm the inverter's transfer time against what your ATMs and branch server tolerate.
  • Four-day installs are only realistic when array, battery and inverter ship as one pre-tested package.

Frequently Asked Questions

How much of a branch's load can 50 kW cover?

The daytime base load β€” lighting, teller positions, ATM, server and communications. Air conditioning is the largest single item in most branches and is usually left to the grid or to a separate chiller schedule.

How long does the battery run the branch?

Eight hours or more at average branch load. The arithmetic behind that figure is 150 kWh Γ· 8 h β‰ˆ 19 kW of average critical load, so the real answer for your branch depends on which circuits you put behind the battery.

What happens when the grid comes back?

The hybrid inverter resynchronises and returns to solar-plus-grid operation, with the battery recharging from the array first. Transfer is automatic; what matters is that the switch-over time sits inside what your ATMs and server tolerate.

Is 85% grid independence realistic for a branch?

It is the figure recorded on this site, and it is achievable because branch load peaks during business hours β€” exactly when the array is producing. Sites with heavy night loads or 24-hour cooling will land lower.

How long do the batteries last?

The pack is rated for 6,000 cycles. Real calendar life depends on depth of discharge and ambient temperature, and both are set by how the system is configured rather than by the cell datasheet alone.

Solar system for bank: What to Replicate

Branch banking cannot go dark: ATMs, teller terminals and network equipment need continuous power, and outages are routine across much of West Africa. A solar system for bank branches is sized against the full branch load rather than lighting alone, with several hours of battery autonomy built in. Our 40–125kVA BESS line is the standard building block for a solar system for bank rollouts, so the same design can be repeated across dozens of branches. If you are costing a solar system for bank, send us your load profile and your latest electricity or fuel bills β€” we return a sized design, a landed quote and a payback model within 24 hours.

Get the Same Results

Free system design and ROI estimate within 24 hours β€” based on your actual electricity bills.